Grade a building platform into the terrain

The Terrain group grades a level platform into the existing ground: its cut and fill batters run out to the terrain, the finished ground pastes every platform in, and the Site page gives the cut and fill volumes. Here a 16 × 10 m house platform on a sloping plot.

Tool: Platform5 steps · 5 pictures

  1. Start from the plot's existing ground — here a 40 × 30 m terrain from a survey, falling about 2.5 m towards the front. Open the Terrain group on the rail and pick Platform. In the tray, type the platform's Level — 1250 — and a Name; leave Use on Building and the batters at 0 to take the soil's own slopes.

    Start from the plot's existing ground — here a 40 × 30 m terrain from a survey, falling about 2.5 m towards the front. Open the Terrain group on the rail and pick Platform. In the tray, type the platform's Level — 1250 — and a Name; leave Use on Building and the batters at 0 to take the soil's own slopes.
  2. Click the corners of the platform's outline on the terrain, one after the other: the outline follows the pointer at the platform's level.

    Click the corners of the platform's outline on the terrain, one after the other: the outline follows the pointer at the platform's level.
  3. Click the last corner, then the first one again to close the outline. The platform is graded in one edit, its top at 1250 mm: at the back it is cut into the slope and lies under the existing ground; at the front it stands on fill, its batters running down to the ground. The message gives its area; its cut and fill come with the finished ground.

    Click the last corner, then the first one again to close the outline. The platform is graded in one edit, its top at 1250 mm: at the back it is cut into the slope and lies under the existing ground; at the front it stands on fill, its batters running down to the ground. The message gives its area; its cut and fill come with the finished ground.
  4. Pick Finished ground in the Terrain group. The finished ground is made from the existing ground with every platform pasted in — Entity Info lists what it is built from — and a note links to the Site page.

    Pick Finished ground in the Terrain group. The finished ground is made from the existing ground with every platform pasted in — Entity Info lists what it is built from — and a note links to the Site page.
  5. Pick Modules on the top bar, then Site and earthworks, and open the Cut and fill tab: the cut, the fill and the balance, the cut bulked and the fill to bring, the topsoil stripped, and the volumes of each platform.

    Pick Modules on the top bar, then Site and earthworks, and open the Cut and fill tab: the cut, the fill and the balance, the cut bulked and the fill to bring, the topsoil stripped, and the volumes of each platform.

Good to know

  • Fall (%) with a Fall direction gives the platform a sloped top instead of a level one.
  • Cut batter and Fill batter are H per 1 V: 1.5 is a 3:2 slope. At 0 they take the soil's own slopes.
  • Where two platforms overlap, the later one wins; the finished ground's Entity Info lists them in order, with Move up and Move down.
  • The Site page's Import tab reads a survey — CSV points, an ESRI ASCII grid or LandXML, up to 100 000 points — and shows it before anything is added.
  • Contours draws a terrain's minor and major contours; Profile opens the long section of the existing and finished ground along a line; Setting-out puts a point with its map coordinates at each corner of the platforms you click.

Recorded in Kozorosa by the help recorder, which checked that the result is in the model.